Title: Approval of time extension for the Shell Service Station Remodel and New Drive-Through Automatic Car Wash located at 2640-2658 N. Santiago Boulevard (Conditional Use Permit No. 3039-17, Conditional Use Permit No. 3054-17, Design Review No. 4898-17, and Minor Site Plan Review No. 0896-17).
Attachments: 1. Staff Report, 2. Attachment 1 Letter from Surinder Multani dated February 20, 2024, 3. Attachment 2 Planning Commission Resolution No. PC 28-21 dated November 15, 2021, 4. Attachment 3 Planning Commission Staff Report dated November 15, 2021, 5. Attachment 4 Planning Commission Minutes dated November 15, 2024, 6. Attachment 5 Planning Commission Approved Project Plans
TO: Chair and Members of the Planning Commission

THRU: Anna Pehoushek, Assistant Community Development Director

FROM: Monique Schwartz, Senior Planner


1. SUBJECT
title
Approval of time extension for the Shell Service Station Remodel and New Drive-Through Automatic Car Wash located at 2640-2658 N. Santiago Boulevard (Conditional Use Permit No. 3039-17, Conditional Use Permit No. 3054-17, Design Review No. 4898-17, and Minor Site Plan Review No. 0896-17).
body
2. SUMMARY
A request to extend the entitlements for a proposal to renovate an existing full-service gas station to include the conversion of existing service bays to convenience store area, expansion of the convenience store building, construction and operation of a new drive-through automatic car wash, related site improvements, and the sale of alcoholic beverages for off-site consumption.
3. RECOMMENDED ACTION
recommendation
Approve a one-year time extension for all entitlements, including Conditional Use Permit No. 3039-17, Conditional Use Permit No. 3054-17, Design Review No. 4898-17, and Minor Site Plan Review No. 0896-17.
end
4. AUTHORIZING GUIDELINES
Orange Municipal Code (OMC) Section 17.08.060 authorizes the body granting final approval for a land use entitlement (in this case the Planning Commission) to extend the period upon which to commence use or construction of the land use entitlement by a period of up to one year. The person seeking such an extension must submit a written request to the Community Development Director in a form acceptable to the Director. The written request should be submitted at least 45 days prior to the expiration date and at a minimum shall explain the extenuating circumstances that have delayed construction or use of the land use entitlement. A request for an extension shall not require public notice provided that no conditions or other requirements are added, deleted, or modified.

5. DISCUSSION AND BACKGROUND
On November 15, 2021, the Planning Comm...