TO: Honorable Mayor and Members of the City Council
THRU: Tom Kisela, City Manager
FROM: Christopher Cash, Public Works Director
1. Subject
title
Notice of Completion and Acceptance for Steel Streetlight Replacement, Fiscal Year 2021-2022 Project; Bid No. 21-22.36 (SP-4196).
body
2. Summary
The City of Orange entered into a contract with California Professional Engineering Inc., to furnish and install 22 Streetlight poles, at various locations throughout the City. The work was completed to the satisfaction of the Public Works Department.
3. Recommended Action
recommendation
1. Accept Steel Streetlight Replacement, Fiscal Year 2021-2022 Project as complete.
2. Authorize City Clerk to file Notice of Completion with the Orange County Clerk-Recorder’s Office.
end
4. ATTACHMENTS
• Notice of Completion and Acceptance