Award of Contract to CEM Construction Corporation for Annual Sewer Replacement/Maintenance Fiscal Year 2023-2024; Bid No. 23-24.35 (S-250).
body
2. SUMMARY
Bids for the Annual Sewer Replacement/Maintenance Fiscal Year 2023-2024 were received and opened on June 6, 2024. Eight bidders responded to the notice inviting bids. The apparent low bidder is CEM Construction Corporation of Downey, California in the amount of $2,079,170.
3. RECOMMENDED ACTION
recommendation
Approve the contract with CEM Construction Corporation in the total amount of $2,287,087, representing an original bid amount of $2,079,170, plus a 10% contingency of $207,917, for Annual Sewer Replacement/Maintenance Fiscal Year 2023-2024; and authorize the Mayor and City Clerk to execute on behalf of the City.
end
4. FISCAL IMPACT
The expense for this contract is $2,287,087 and will be funded in Sewer Line Maintenance/Replacement through:
520.5011.56200.15508 Sewer Construction $2,287,087
5. STRATEGIC PLAN GOALS
Goal 1: Provide for a safe community
b: Provide and maintain infrastructure necessary to ensure the safety of the public.
Goal 4: Provide outstanding public service
b: Provide facilities and services to meet customer expectations.
6. DISCUSSION AND BACKGROUND
The Annual Sewer Replacement/Maintenance Fiscal Year 2023-2024 is designed to upgrade the City's aging sewer infrastructure by replacing pipes that are structurally deficient, improving pipeline capacity, and minimizing maintenance issues resulted from damaged sewer mainlines. This project will consist of sewer line maintenance funded by the Sewer Construction Fund.
This project will replace/upsize approximately 4,200 linear feet of existing 6-inch vitrified clay pipe (VCP) with 8-inch VCP and 200 linear feet of existing 6-inch VCP with 10-inch VCP in various loc...