File #: 25-0468    Version: 1
Type: Consent - Agreements Status: Passed
File created: 7/25/2025 In control: Orange City Council
On agenda: 8/12/2025 Final action: 8/12/2025
Title: Cooperative agreement with the City of Santa Ana for the Main Street Slurry Seal and Resurfacing Project.
Attachments: 1. Staff Report, 2. Cooperative Agreement with City of Santa Ana

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Jarad Hildenbrand, City Manager

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Cooperative agreement with the City of Santa Ana for the Main Street Slurry Seal and Resurfacing Project.

body

2.                     Summary

The City of Santa Ana and the City of Orange have prepared a cooperative agreement outlining each city’s financial responsibility for the Main Street Slurry Seal and Resurfacing project.

3.                     Recommended Action

recommendation

Approve the cooperative agreement with the City of Santa Ana in the amount of $104,670, representing the City of Orange’s share of the estimated construction costs plus a 15% contingency, for the Main Street Slurry Seal and Resurfacing Project; and authorize the Mayor and City Clerk to execute on behalf of the City.

end

4.                     Fiscal Impact

The expense for this cooperative agreement is $104,670 and will be funded through Measure M - Traffic Improvement (263):

263.5011.56330.13120                     Pavement Management Program

5.                     Strategic Plan Goals

Goal 5: Improve infrastructure, mobility, and technology.

6.                     Discussion and Background

The Main Street Slurry Seal and Resurfacing Project is designed to upgrade the pavement on Main Street from Memory Lane to the northern City of Santa Ana city limit and approximately 250 feet of Town and Country east of Main Street. Main Street is an existing six-lane major arterial located on the border of the City of Orange and City of Santa Ana, lying partially in Orange and partially in Santa Ana. Project improvements include grinding localized areas of the existing asphalt concrete pavement and repaving the street with asphalt concrete base course, applying a slurry seal over the entire project area, adjusting surface utility covers, replacing traffic loop detectors, traffic striping, curb and gutter, and ADA ramps.

The City of Orange was approached by the City of Santa Ana to enter into this cooperative agreement to ensure project continuity, as the project lies within the limits of both jurisdictions. The project design was prepared and completed by the City of Santa Ana and reviewed by Public Works staff prior to advertisement for construction.

On June 26, 2025, the City of Santa Ana received the project bids. The lowest bidder was All American Asphalt, at a total bid of $792,572.50. The City of Santa Ana will pay for approximately 89% of the project cost, with the remaining 11% to be paid by the City of Orange.  Staff recommends that the City Council approve the Cooperative Agreement with the City of Santa Ana.

7.                     ATTACHMENT

                     Cooperative Agreement with the City of Santa Ana