File #: 22-0491    Version: 1
Type: Administrative Reports Status: Agenda Ready
File created: 8/16/2022 In control: Orange City Council
On agenda: 10/24/2023 Final action:
Title: Approval of plans and specifications for the City of Orange Corporation Yard Renovations Project, Phase I; authorization to advertise for bids; and finding of CEQA exemption.
Attachments: 1. Staff Report

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Tom Kisela, City Manager                                          

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Approval of plans and specifications for the City of Orange Corporation Yard Renovations Project, Phase I; authorization to advertise for bids; and finding of CEQA exemption.

body

2.                     Summary

Approval of plans and specifications for the City of Orange Corporation Yard Renovations Project, Phase I and authorization to advertise for bids. The total estimated construction cost is $4 million.

3.                     Recommended Action

recommendation

Approve plans and specifications and authorize advertising for Bid No. 23-24.14.

end

4.                     Fiscal Impact

The total expenditure for Phase I of the project is $4.12 million and will be funded through:

Corp Yard Renovations (12982)                                           Sewer Maintenance (220)                                           $1,677,000                     

Gas Tax (270)                                                                           287,000

                                                                                                                              Capital Projects (500)                                               1,000,000

City Infrastructure Bond (553)                        1,000,000

City Facility Improvements (19809)                      City Trf: Tax Exempt Bonds (954)                           156,000                                                                                                                                                                                                                  Total:                                           $4,120,000

5.                     Strategic Plan Goals

Goal 1: Provide for a safe community

b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service

b: Provide facilities and services to meet customer expectations.

6.                     Discussion and Background

The City’s Corporation Yard (Corp Yard) located off Struck Avenue, was designed in 1975. Since that original plan, there have been minimal layout changes.  With the recent sale of the eastern third of the Corp Yard for the Valencia Gardens Housing Project and changes to equipment and technology in the past 46 years, a reconfiguration of the facility is needed for continued operations.

The City retained an architectural firm to perform a feasibility study to redesign the layout and increase the functionality of the remaining space.  Phase I of this project focuses on improving the Corp Yard’s space allocation, providing parking spaces for 100 employees, designating raw material storage areas, enhancing paths of travel and safety, maximizing equipment and vehicle storage, and redistributing the current storage for the Police Department.  It also includes upgrading necessary improvements to comply with National Pollutant Discharge Elimination System (NPDES) environmental requirements. Other modifications include surface and underground drainage systems, lighting, landscaping, perimeter walls including the Police Department frontage along Struck, striping, and other onsite improvements as needed.  Future phases of the project focus on pavement reconstruction, additional site lighting, and prefab metal buildings for Public Works, Community Services, and Fire Departments.  The design of this project started in late 2021 and is now complete and ready to bid.

The total estimated project cost for multiple phases of this project are $10.6 million dollars, this includes a construction cost of $9.2 million dollars, a 15% contingency, and construction management costs. Current available funding for the project is $4.12 million.   Currently, the Phase I bid includes all the underground improvements, surrounding 600 linear feet of walls for both the Corp Yard and adjacent Police Department Headquarters, Police Department storage area and building, material staging areas, 34,000 square feet of pavement reconstruction, enhanced main gate access, lighting and striping.  In preparation for potential escalated construction costs, the bid includes a few deductible alternate bid items to further control costs and stay within budget.

Multiple funding sources are being used to support the project's construction phases, as these funds support the daily activities of the Corp Yard and the City. Future additional funding will likely be necessary to fully execute future phases and optimal buildout of the project.

7.                     ENVIRONMENTAL REVIEW

Categorical Exemption:  The proposed project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) per State CEQA Guidelines Section 5301 (Class 1 - Existing Facilities) and Section 5311 (Class 11 -Accessory Structures), because the project involves the maintenance and reconfiguration of the existing Corporation Yard and the addition of accessory storage structures.  No public review is required.