Legislation Details

File #: 24-0149    Version: 1
Type: Consent - Purchase Status: Passed
File created: 2/28/2024 In control: Orange City Council
On agenda: 3/12/2024 Final action: 3/12/2024
Title: Approval of payment to Southern California Edison for new electrical service for Well No. 28 located at 225 W. Maple Avenue.
Attachments: 1. Staff Report, 2. SCE New Meter and Service Plan, 3. SCE Invoice

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Tom Kisela, City Manager

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Approval of payment to Southern California Edison for new electrical service for Well No. 28 located at 225 W. Maple Avenue.

body

2.                     Summary

Southern California Edison submitted a payment request in the total amount of $81,005.98 for the design and installation of new electrical service for Well No. 28.

3.                     Recommended Action

recommendation

Approve payment to Southern California Edison in the amount of $81,005.98 for the design and installation of electrical service to Well No. 28.

end

4.                     Fiscal Impact

The expense for this purchase is $81,005.98 and will be funded through:

600.8011.56411.18120                     Water Fund (600)                     Well 28 Construction

5.                     Strategic Plan Goals

Goal 1: Provide for a safe community

b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service

b: Provide facilities and services to meet customer expectations.

6.                     Discussion and Background

Phase 2 of the Well No. 28 project consists of the installation of the well head, Ion Exchange vessels, piping, electrical and chemical buildings, screen walls, and the public pocket park. This project requires a new underground service and electrical meter from Southern California Edison (SCE) to power the well pump, motor, miscellaneous lighting, and other electrical components. While the contractor is tasked with providing all on-site electrical equipment, the City, as the owner, is responsible for requesting electrical service from SCE to the site. SCE has completed the design for the new service and submitted an invoice for both the design and installation in the total amount of $81,005.98. SCE’s installation will start upon receiving the requested payment.  Staff is requesting the City Council approve the payment to SCE for the new service at Well 28.

7.                     ATTACHMENTS

•                     SCE New Meter and Service Plan

•                     SCE Invoice