Legislation Details

File #: 26-0566    Version: 1
Type: Consent - Contracts Status: Agenda Ready
File created: 9/17/2026 In control: Orange City Council
On agenda: 10/13/2026 Final action:
Title: Notice of Completion and Acceptance of Bridge Preventive Maintenance/Repair
Attachments: 1. Staff Report, 2. Notice of Completion and Acceptance

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Jarad Hildenbrand, City Manager

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Notice of Completion and Acceptance of Bridge Preventive Maintenance/Repair

body

2.                     Summary

This project consisted of isolated, small-scale repairs on eight bridges within the City’s limits; three bridges span Santiago Creek and five span the Santa Ana River, all located within the Santa Ana River Watershed.

The project included the repair of concrete spalls on the bridge decks, side rails, sidewalks, and bridge girders, and cleaning and sealing the bridge decks.

The City of Orange entered into a contract with Peterson-Chase General Engineering Construction, Inc. The work was completed to the satisfaction of the Public Works Department.

The approved project budget was $2,696,416.00 with a 5% contingency. The final construction cost was $1,784,073.00. The project was completed under budget primarily due to the reduction in the contract’s scope of work related to the Ball Road Bridge. During construction, field assessments revealed that the Ball Road Bridge requires comprehensive structural rehabilitation rather than the isolated preventive maintenance originally scoped. The cost for this unforeseen additional scope of work is approximately $1.5 million dollars, which exceeds the allowable change order limits per the federal requirements and public contract code.

In coordination with our federal funding partners, the Public Works Department is developing dedicated design plans for the Ball Road Bridge and will advertise the comprehensive rehabilitation of the Ball Road Bridge as a standalone project.  Staff continue to seek grant funding opportunities for this project.

3.                     Recommended Action

recommendation

1.                     Accept the Bridge Preventive Maintenance/Repair project, Bid No. 24-25.23, SP-3880, as complete.

2.                     Authorize the City Clerk to file the Notice of Completion with the Orange County Clerk-Recorder’s Office.

end

4.                     ATTACHMENTS

•                     Notice of Completion and Acceptance