TO: Honorable Mayor and Members of the City Council
THRU: Jarad Hildenbrand, City Manager
FROM: Christopher Cash, Public Works Director
1. Subject
title
Award of Contract to G.M. Sager Construction Co., Inc. for Asphalt Repair services, and finding of California Environmental Quality Act (CEQA) exemption
body
2. Summary
Bids were solicited for asphalt repair at various locations to restore roadway surfaces disturbed by waterline breaks. Two bidders responded, and G.M. Sager Construction Co., Inc. is the apparent low bidder in the amount of $134,000.
3. Recommended Action
recommendation
1. Approve the contract with G.M. Sager Construction Co., Inc. in the total amount of $147,400, representing an original bid amount of $134,000, plus a 10% contingency of $13,400, for asphalt repair; and authorize the Mayor and City Clerk to execute on behalf of the City.
2. Find that the proposed project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) Per State CEQA Guidelines 15301 (Class 1 - Existing Facilities).
end
4. Fiscal Impact
The expense for this contract is $147,400 and will be funded through Water (600):
600-5803-53201- Repair & Maintenance Supplies
5. Strategic Plan Goals
Goal 5: Improve Infrastructure, Mobility, and Technology
6. Discussion and Background
The City’s Water Utility experiences water main breaks and leaks throughout the year. While City crews handle the initial excavation, pipe repair, and temporary surfacing, permanent asphalt restoration requires specialized contractor services. Through an informal bid process staff solicited bids from four reputable companies for asphalt repair and two bids were received:
Company Amount
1. G.M. Sager Construction Co., Inc. $134,000.00
2. Big Ben Engineering, Inc. $240,250.00
All American Asphalt was nonresponsive.
Staff checked the references and qualifications of G.M. Sager Construction Co., Inc. and found them to be acceptable, with adequate years of experience in completing similar projects. G.M. Sager Construction Co., Inc. has previously completed asphalt restoration projects for the City, consistently delivering high-quality work in a timely and efficient manner. Therefore, staff recommend awarding the contract to G.M. Sager Construction Co., Inc. in the amount of $147,400, representing an original bid of $134,000, plus a 10% contingency of $13,400. Construction is scheduled to commence in December 2026, with a projected completion window of 30 calendar days.
7. ENVIRONMENTAL REVIEW
The proposed project is categorically exempt (Class 1) from the provisions of the California Environmental Quality Act (CEQA) under CEQA Guidelines Section 15301. Section 15301 categorically exempts projects that consist of maintenance, replacement or reconstruction of existing facilities where the facilities will be located on the same site as the facilities replaced and will have substantially the same purpose and capacity as the facilities replaced.
8. ATTACHMENTS
• Contract with G.M. Sager Construction Co., Inc.