Title: Review and discuss the Santiago Creek Strategic Plan - Segment Two recommended projects.
Attachments: 1. Staff Report, 2. Santiago Creek Strategic Plan - Segment Two- Commissioner Galera, 3. Santiago Creek Trail - Segment Two - Commissioner Galera, 4. Santiago Creek Strategic Plan - Segment Two - Commissioner Hillman, 5. Santiago Creek Strategic Plan - Segment Two - Commissioner Knight

TO:                     Chair and Members of the Santiago Creek Commission

 

FROM:                     Tom Kisela, City Manager

                                                                                                                               

1.                     Subject

title

Review and discuss the Santiago Creek Strategic Plan - Segment Two recommended projects.

body

2.                     Summary

On January 22, 2025, the Santiago Creek Commission discussed the property ownership and area map as well as the overall themes for the Santiago Creek Strategic Plan - Segment Two. By establishing themes for Santiago Creek Strategic Plan - Segment Two first, the Santiago Creek Commission created a focus to guide project recommendations that will be included in the final Santiago Creek Strategic Plan. The purpose of this item is to finalize project recommendations that were submitted for Santiago Creek Strategic Plan - Segment Two.

3.                     Recommended Action

recommendation

Review, discuss, and finalize the recommended projects for Santiago Creek Strategic Plan - Segment Two.

end

4.                     Fiscal Impact

None.

5.                     Strategic Plan Goals

Goal 4: Improve Infrastructure, Mobility, and Technology.

6.                     Discussion and Background

At the January 22, 2025, Santiago Creek Commission (SCC) meeting, the SCC reviewed the area and property ownership map for Santiago Creek Strategic Plan - Segment Two (Segment Two). In reviewing the Segment Two area and property ownership map first, the SCC identified unique characteristics and themes that should inform project recommendations for Segment Two.

After identifying underlying themes for Segment Two at the January 22nd SCC meeting, Commissioners have had the opportunity to develop project recommendations for consideration and discussion at the April 23, 2025, SCC meeting. Projects submitted before this agenda’s publication are attached to this report for review and discussion.

As the SCC continues to work through each segment, provided below is the proposed schedule through calendar year 2025.

 

 

Discussion Item(s)

Meeting Date

Segment One recommended projects and vision statement as well as Segment Two themes.

January 22, 2025

Segment Two recommended projects and vision statement as well as Segment Three themes.

April 23, 2025

Segment Three recommended projects and vision statement.

July 23, 2025

Review draft Santiago Creek Strategic Plan.

October 22, 2025

Submit the draft Santiago Creek Strategic Plan to the City Council for approval.

December 9, 2025, City Council Meeting

 

7.                     ATTACHMENTS

                     Attachment 1 Santiago Creek Strategic Plan - Segment Two - Vice Chair Galera

                     Attachment 2 Santiago Creek Strategic Plan - Segment Two Trail - Vice Chair Galera

                     Attachment 3 Santiago Creek Strategic Plan - Segment Two - Commissioner Hillman

                     Attachment 4 Santiago Creek Strategic Plan - Segment Two - Commissioner Knight