File #: 25-0601    Version: 1
Type: Consent - Contracts Status: Agenda Ready
File created: 10/17/2025 In control: Orange City Council
On agenda: 11/12/2025 Final action:
Title: Award of Contract to All Cities Engineering, Inc. for Annual Pipeline Renewal Project; Bid No. 25-26.04.
Attachments: 1. Staff Report, 2. Location Map, 3. Contract with All Cities Engineering, Inc., 4. Bid Abstract

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Jarad Hildenbrand, City Manager

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Award of Contract to All Cities Engineering, Inc. for Annual Pipeline Renewal Project; Bid No. 25-26.04.

body

2.                     Summary

Eight bids for the Annual Pipeline Renewal Project (W-725) were received and opened on October 2, 2025. The apparent low bidder is All Cities Engineering, Inc. for $1,190,075.

3.                     Recommended Action

recommendation

Approve the contract with All Cities Engineering, Inc. in the amount of $1,309,083, representing an original bid amount of $1,190,075, plus a 10% contingency of $119,008 for the Annual Pipeline Renewal Project; and authorize the Mayor and City Clerk to execute on behalf of the City.

end

4.                     Fiscal Impact

The expense for this contract is $1,309,083 and will be funded through Water (600):

600-5803-85103-255085                                          Pipeline Renewal Project                     

5.                     Strategic Plan Goals

Goal 5: Improve Infrastructure, Mobility, and Technology

 

6.                     Discussion and Background

Existing water mains on N. Santiago Boulevard, E. Villa Vista Way, E. Riding Way, El Sereno Dr., E. Riding Way, and N. Bailey Dr. are scheduled to be replaced as part of the Annual Pipeline Renewal Project. These water mains were constructed between the 1950’s and 1960’s and have reached the end of their useful life. The mains are also undersized per current industry standards. The new water mains will provide a more reliable water service and fire protection for the residents in the area.

The City Council previously approved advertisement for bids on September 9, 2025.  The bids were received and opened on October 2, 2025. Eight bidders responded as follows:

CONTRACTOR                                                                                                                               AMOUNT

1. All Cities Engineering Inc., Downey, CA                                                                                     $ 1,190,075

2. Big Ben Engineering, Irvine, CA                                                                                                          $ 1,336,310

3. Dominguez General Engineering, Inc., Pomona, CA                                           $ 1,454,000

4. Stephen Doreck Equipment Rentals, Inc., Pico Rivera, CA                      $ 1,570,808

5. CEM Construction Corporation, Montebello, CA                                                                $ 1,749,150

6. Giles Engineering Associates, Inc., Orange, CA                                                                $ 1,760,611

7. Ramona, Inc., Baldwin Park, CA                                                                                                          $ 2,023,255

8. CHI Construction, Fullerton, CA                                                                                                         $ 2,421,975

All Cities Engineering, Inc. is the apparent responsive low bidder. Staff checked the references and qualifications for All Cities Engineering, Inc. and found them to be acceptable, with adequate years of experience in completing contracts of a similar nature to this project. The Contractor has completed pipeline replacement projects with many surrounding agencies. Therefore, staff recommend that All Cities Engineering be awarded the contract in the amount of $1,190,075, plus a 10% contingency for a total amount of $1,309,083. Construction is scheduled to begin in January 2026 and is expected to be completed within 150 calendar days.

7.                     ATTACHMENTS

                     Location Map

                     Contract with All Cities Engineering, Inc.

                     Bid Abstract