File #: 24-0153    Version: 1
Type: Consent - Contracts Status: Passed
File created: 2/28/2024 In control: Orange City Council
On agenda: 4/23/2024 Final action: 4/23/2024
Title: Award of Contract to Monet Construction, Inc. for Corporation Yard Renovation Project - Police Storage Facility (Phase 1A); Bid No.23-24.23.
Attachments: 1. Staff Report, 2. Bid Abstract, 3. Contract with Monet Construction, Inc.

TO:                                          Honorable Mayor and Members of the City Council

 

THRU:                     Tom Kisela, City Manager

                                                                                                          

FROM:                     Christopher Cash, Public Works Director

                                          

                     

1.                     Subject

title

Award of Contract to Monet Construction, Inc. for Corporation Yard Renovation Project - Police Storage Facility (Phase 1A); Bid No.23-24.23.

body

2.                     Summary

Bids for the City of Orange Corporation Yard Renovation Project-Police Storage Facility (Phase 1A) were received and opened on March 21, 2024. Five bidders responded to the notice inviting bids. The apparent low bidder is Monet Construction, with a bid of $1,794,529.

3.                     Recommended Action

recommendation

1.                     Authorize the appropriation of $500,000 from the unreserved fund 553 balance to:

553.5028.56015.12982 City Trf. Tax Exempt Bonds City Facility Improvements

2.                     Approve the contract with Monet Construction, Inc. in the amount of $1,794,529 for the City of Orange Corporation Yard Renovation Project-Police Storage Facility (Phase 1A); and authorize the Mayor and City Clerk to execute on behalf of the City.

 

end

4.                     Fiscal Impact

The expense for this contract is $1,794,529 and will be funded through:

500.5028.56015.12982                     Corp Yard Renovation                      $   230,340

553.5028.56015.12982                     Corp Yard Renovation                     $1,500,000

954.5028.56020.19809                     City Facility Improvements                     $     64,189

                                                                                                                              Total                                          $1,794,529

Upon approval of the appropriation, the estimated fund balance in the City Infrastructure Bond (553) fund at June 30, 2024 will be $271,146.

5.                     Strategic Plan Goals

Goal 1: Provide for a safe community

b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service

b: Provide facilities and services to meet customer expectations.

6.                     Discussion and Background

The City of Orange Corporation Yard Renovation Project -Police Storage Facility (Phase 1A) includes a new police storage building with associated electrical improvements and lighting, storm drain improvements, and a new security perimeter wall for the adjacent Police Department employee parking lot. This phase brings the Corporation Yard one step closer to the planned site reconfiguration, which features a more efficient and enhanced layout due to the downsizing of the property.

The City Council previously approved an advertisement for bids on October 24, 2023. The bid solicitation was advertised on February 29, 2024, for a period of three weeks, and bids were opened on March 21, 2024. Five bids were received as follows:

1.                     Monet Construction, Inc., Tujunga                                                                                                         $1,631,390

2.                     Horizons Construction Co., Orange                                                                                                         $1,649,500

3.                     MBC Enterprises, Inc., Westminster                                                                                                         $2,055,900

4.                     Metro Builders and Engineering Group, Ltd., Newport Beach                                          $2,070,996

5.                     Kazoni, Inc., Costa Mesa                                                                                                                                                   $2,143,000

The low bid is about 25% higher than the engineer’s estimate. This may be due to the increasing costs of construction and materials. Staff checked the references and qualifications for Monet Construction, Inc. and found them to be acceptable, with adequate years of experience in completing contracts of a similar nature to this project. Therefore, staff recommends that Monet Construction, Inc. be awarded the contract in the total amount of $1,794,529, representing the original amount of $1,631,390, plus a 10% contingency of $163,139 for the City of Orange Corporation Yard Renovation Project -Police Storage Facility (Phase 1A).

Construction is scheduled to begin in June 2024 and is expected to be completed in 120 calendar days. Additionally, staff will continue the phased approach for the Corporation Yard Project, with Phase 1B scheduled to be advertised in summer.

7.                     ATTACHMENTS

                     Bid Abstract

                     Contract with Monet Construction, Inc.