Title: Award of Contract to Golden Coast Construction for Community Development Block Grant Fiscal Year 2025-2026 Americans with Disabilities Act Wheelchair Access Ramp Replacement
Attachments: 1. Staff Report, 2. Contract with Golden Coast Construction, 3. Bid Abstract
TO: Honorable Mayor and Members of the City Council

THRU: Jarad Hildenbrand, City Manager

FROM: Christopher Cash, Public Works Director


1. SUBJECT
title
Award of Contract to Golden Coast Construction for Community Development Block Grant Fiscal Year 2025-2026 Americans with Disabilities Act Wheelchair Access Ramp Replacement
body
2. SUMMARY
Bids for the Community Development Block Grant Fiscal Year 2025-2026 Americans with Disabilities Act Wheelchair Access Ramp Replacement Project were received and opened on June 18, 2026 (Bid No. 25-26.19; SP-4330). Six bidders responded to the notice inviting bids. The apparent low bidder is Golden Coast Construction of La Habra, California in the amount of $61,988.
3. RECOMMENDED ACTION
recommendation
1. Approve the contract with Golden Coast Construction in the total amount of $71,286, representing an original bid amount of $61,988, plus 15% contingency of $9,298, for the construction of ten ADA Wheelchair Access Ramps; and authorize the Mayor and City Clerk to execute on behalf of the City.
2. Authorize the continuing appropriation of $97,723 from the Community Development Block Grant (310) Fiscal Year 2026 budget:
310-6411-88101-265092-20 ADA Improvements
3. Authorize the following budget transfer in Community Development Block Grant (310):
From: 310-6411-88101-265092-20 ADA Improvements $97,723
To: 310-6411-87102-265092-20 ADA Improvements $97,723

end
4. FISCAL IMPACT
The expense for this contract is $71,286.00 and will be funded through Community Development Block Grant (310):
310-6411-88102-265092-20 ADA Improvements
5. STRATEGIC PLAN GOALS
Goal 5: Improve Infrastructure, Mobility, and Technology

6. DISCUSSION AND BACKGROUND
The Federal Community Development Block Grant Program (CDBG) provides grant funds to enable eligible localities to construct public improvements in Low- and Moderate-Income Areas within their jurisdiction. The proposed wheelchair ramp improvements project was approved thro...