Legislation Details

File #: 26-0180    Version: 1
Type: Consent - Contracts Status: Passed
File created: 3/24/2026 In control: Orange City Council
On agenda: 4/28/2026 Final action: 4/28/2026
Title: Award of Contract to DD Systems, Inc., dba Ace CD, Inc., for construction of the Skatepark at Grijalva Park Project
Attachments: 1. Staff Report, 2. ???Attachment 1 Skatepark Design Rendering, 3. Attachment 2 Bid Abstract Summary, 4. Attachment 3 Contract with DD Systems, Inc
TO: Honorable Mayor and Members of the City Council

THRU: Jarad Hildenbrand, City Manager

FROM: Leslie Hardy, Community and Library Services Director


1. SUBJECT
title
Award of Contract to DD Systems, Inc., dba Ace CD, Inc., for construction of the Skatepark at Grijalva Park Project
body
2. SUMMARY
Award of a construction contract for the installation of a new concrete skatepark facility featuring a custom-designed skate court with bowl, rails, and other riding elements. The scope of work includes installation of area and lighting with supporting electrical infrastructure, a prefabricated restroom building, and creation of paved access routes. Additional improvements include a shaded spectator seating area, enhanced landscaping, and various skatepark amenities.

3. RECOMMENDED ACTION
recommendation
1. Approve the contract with DD Systems, Inc., dba Ace CD, Inc. in the amount of $2,525,836.50 for construction of the Skatepark at Grijalva Park Project (257012); and authorize the Mayor and City Clerk to execute on behalf of the City.
2. Authorize the appropriation of $1,041,101.00 from the Park Acquisition (Infill) Fund (510) unreserved fund balance to account 510.7201.84101 (257012-80) CIP - Skatepark at Grijalva Project.
end
4. FISCAL IMPACT
The total expense for this construction contract is $2,525,836.50. The overall project will be funded through Park Acquisition (Infill) (510), Capital Projects (500), and County Park Grants Funds (551), respectively.

Upon approval of this appropriation, the estimated Park Acquisition (510) fund balance at June 30, 2026 will be $6,343,032.00.

5. STRATEGIC PLAN GOALS
Goal 3: Enhance Public Communication Strategy and Quality of Life
Objective 3.7: Continue to offer high quality and efficient city led recreation programs

6. DISCUSSION AND BACKGROUND
At the November 15, 2022 City Council meeting, the City Council directed staff to use $1.75 million in park development fees to build a skatepark at Grijalva Pa...