TO: Honorable Mayor and Members of the City Council
THRU: Jarad Hildenbrand, City Manager
FROM: Christopher Cash, Public Works Director
1. SUBJECT
title
Acceptance and appropriation of $853,000 in Orange County Transportation Authority Congestion Mitigation and Air Quality Improvement Program grant funds, and appropriation of $116,000 in match funds for the Santiago Creek Bike Trail Extension Project.
body
2. SUMMARY
The Orange County Transportation Authority approved the allocation of Congestion Mitigation and Air Quality Improvement Program funding and has awarded the City of Orange $853,000 for the Santiago Creek Bike Trail Extension Project. The City is also required to provide $116,000 in match funds for this project. This funding will be used to complete the environmental and engineering phase of the project.
3. RECOMMENDED ACTION
recommendation
1. Accept into the City's Other Federal Grants (399) revenue budget $853,000 in grant funds from the Orange County Transportation Authority Congestion Mitigation and Air Quality Improvement Program:
399-5101-43301-265008-43 Santiago Creek Bike Trail Extension Project
2. Authorize the appropriation of $853,000 to Other Federal Grants (399):
399-5101-87102-265008 Santiago Creek Bike Trail Extension Project
3. Authorize the appropriation of $116,000 from Capital Projects (500) to:
500-5101-87102-265008 Santiago Creek Bike Trail Extension Project
end
4. FISCAL IMPACT
The expense for this project is $969,000 and will be funded through Other Federal Grants (399) and Capital Projects (500) respectively:
399-5101-87102-265008- Santiago Creek Bike Trail Extension Project $853,000
500-5101-87102-265008- Santiago Creek Bike Trail Extension Project $116,000
Upon the approval of this appropriation, the estimated Capital Projects (500) fund balance at June 30, 2026, will be $9,519,902.
5. STRATEGIC PLAN GOALS
Goal 5: Improve Infrastructure, Mobility, and Technology