Title: Approval of plans and specifications for Annual Pipeline Renewal project and authorization to advertise for bids; and finding of California Environmental Quality Act (CEQA) exemption.
Attachments: 1. Staff Report, 2. Location Map
TO: Honorable Mayor and Members of the City Council

THRU: Jarad Hildenbrand, City Manager

FROM: Christopher Cash, Public Works Director


1. SUBJECT
title
Approval of plans and specifications for Annual Pipeline Renewal project and authorization to advertise for bids; and finding of California Environmental Quality Act (CEQA) exemption.
body
2. SUMMARY
Construction plans and specifications are completed for the Annual Pipeline Renewal, and the project is ready to be advertised for bids. The estimated construction cost is $1,395,000.
3. RECOMMENDED ACTION
recommendation
1. Approve the plans and specifications and authorize advertising for Bid. No. 25-26.04, Annual Pipeline Renewal project.
2. Find the project Categorically Exempt from the California Environmental Quality Act per Guidelines Section 15302.
end
4. FISCAL IMPACT
None.
5. STRATEGIC PLAN GOALS
Goal 5: Improve Infrastructure, Mobility, and Technology

6. DISCUSSION AND BACKGROUND
Existing water mains on E. Villa Vista Way, E. Riding Way, El Sereno Dr., N Bailey Dr., and Santiago Blvd. are scheduled to be replaced as part of the Annual Pipeline Renewal project. These pipelines were constructed between the 1950's and 1960's and have reached the end of their useful life. They are also undersized per current industry standards. Additionally, most of these water mains are in the sidewalk area making repairs and pavement restoration more costly and inconvenient to residents.
The new water mains will be installed in the roadway and will provide more reliable water service and fire protection for the residents in the area. The scope of work consists of utility potholing, installation of approximately 3,560 feet of new water mains, new water meters, lateral services, fire hydrants, valves, fittings, and other appurtenances in accordance with current water industry standards. The engineering cost estimate for this project is $1,395,000. Construction is scheduled to begin in late 2025 and is expec...