Title: First Amendment to Contract with CJ Concrete Construction, Inc. for Annual Concrete Replacement at Various Locations Fiscal Year 2025-2026
Attachments: 1. Staff Report, 2. First Amendment to Contract
TO: Honorable Mayor and Members of the City Council

THRU: Jarad Hildenbrand, City Manager

FROM: Christopher Cash, Public Works Director


1. SUBJECT
title
First Amendment to Contract with CJ Concrete Construction, Inc. for Annual Concrete Replacement at Various Locations Fiscal Year 2025-2026
body
2. SUMMARY
The City of Orange has entered into a contract with CJ Concrete Construction, Inc. for the Annual Concrete Replacement at Various Locations Fiscal Year 2025-2026. Additional locations have been added to the agreed bid unit prices in the amount of $105,100.
3. RECOMMENDED ACTION
recommendation
1. Approve the amendment to the contract with CJ Concrete Construction, Inc. in the amount of $105,100 for Annual Concrete Replacement at Various Locations Fiscal Year 2025-2026; and authorize the Mayor and the City Clerk to execute on behalf of the City.
2. Authorize the continuing appropriation of $161,604.93 from the Fiscal Year 2026 CIP budget account into the Fiscal Year 2027 budget:
500-5101-87102-255702- Pavement Management Program

end
4. FISCAL IMPACT
The expense for this amendment is $105,100 and will be funded through Capital Projects (500):
500-5101-87102-255702-20 Pavement Management Program
5. STRATEGIC PLAN GOALS
Goal 5: Improve Infrastructure, Mobility, and Technology
6. DISCUSSION AND BACKGROUND
The City Council Awarded the Annual Concrete Replacement at Various Locations Fiscal Year 2025-2026 on June 23, 2026, to CJ Concrete Construction, Inc. The project addresses concrete repairs identified by the Public Works Department, replacing sidewalk displacements and lifted curbs and gutters.
The unit bid prices from CJ Concrete Construction, Inc., were very favorable to the City to increase the scope of work. As such, staff recommends adding approximately 4,650 square feet of sidewalk, 600 linear feet of curb and gutter and 150 square feet of driveway approaches.
The awarded contract amount for CJ Concrete Construction, Inc. was $597,8...