File #: 20-087    Version: 2
Type: Consent - Agreements Status: Passed
File created: 8/18/2020 In control: City Council
On agenda: 9/8/2020 Final action: 9/8/2020
Title: Agreement with Sargent Town Planning for preparation of the North Tustin Street Specific Plan.
Attachments: 1. Staff Report, 2. Proposed NTSP Area Map, 3. Request for Proposals, 4. Consultant Services Agreement including Scope and Deliverables, Schedule, and Fee Proposal
TO: Honorable Mayor and Members of the City Council

THRU: Rick Otto, City Manager

FROM: William Crouch, Community Development Director


1. SUBJECT
title
Agreement with Sargent Town Planning for preparation of the North Tustin Street Specific Plan.
body
2. SUMMARY
Consultant Services Agreement with Sargent Town Planning to prepare a North Tustin Street Specific Plan with a not to exceed cost of $445,152 plus a contingency allowance of $54,848.
3. RECOMMENDED ACTION
recommendation
Approve the agreement with Sargent Town Planning in the total amount of $500,000, representing an original contract amount of $445,152, plus a contingency allowance of $54,848, for the creation of the North Tustin Street Specific Plan; and authorize the Mayor and City Clerk to execute on behalf of the City.

end
4. FISCAL IMPACT
The total expenditure, including the contingency, for this agreement is $500,000 and will be funded in the North Tustin Street Specific Plan (30143) through:
Senate Bill 2 (SB-2) Planning Grant Program (312) $240,000
Reimbursable Capital Projects (550) 260,000
Total: $500,000
5. STRATEGIC PLAN GOALS
Goal 2: Be a fiscally healthy community
e: Create an environment to attract, retain, and expand economic opportunities.
Goal 3: Enhance and promote quality of life in the community
c: Support and enhance attractive, diverse living environments.
6. DISCUSSION AND BACKGROUND
The North Tustin Street Corridor became a redevelopment project area in 1983. In conjunction with establishment of the redevelopment area, a zoning classification specific to the area was created, the Commercial-Tustin Redevelopment Area (C-TR) zone. The Tustin Street Design Standards were also adopted at that time. The purpose of these two actions was to reinvigorate and generate property reinvestment in the corridor. The anticipated benefits of the C-TR zoning and design standards came to limite...