File #: 24-0153    Version: 1
Type: Consent - Contracts Status: Passed
File created: 2/28/2024 In control: City Council
On agenda: 4/23/2024 Final action: 4/23/2024
Title: Award of Contract to Monet Construction, Inc. for Corporation Yard Renovation Project - Police Storage Facility (Phase 1A); Bid No.23-24.23.
Attachments: 1. Staff Report, 2. Bid Abstract, 3. Contract with Monet Construction, Inc.
TO: Honorable Mayor and Members of the City Council

THRU: Tom Kisela, City Manager

FROM: Christopher Cash, Public Works Director


1. SUBJECT
title
Award of Contract to Monet Construction, Inc. for Corporation Yard Renovation Project - Police Storage Facility (Phase 1A); Bid No.23-24.23.
body
2. SUMMARY
Bids for the City of Orange Corporation Yard Renovation Project-Police Storage Facility (Phase 1A) were received and opened on March 21, 2024. Five bidders responded to the notice inviting bids. The apparent low bidder is Monet Construction, with a bid of $1,794,529.
3. RECOMMENDED ACTION
recommendation
1. Authorize the appropriation of $500,000 from the unreserved fund 553 balance to:
553.5028.56015.12982 City Trf. Tax Exempt Bonds City Facility Improvements
2. Approve the contract with Monet Construction, Inc. in the amount of $1,794,529 for the City of Orange Corporation Yard Renovation Project-Police Storage Facility (Phase 1A); and authorize the Mayor and City Clerk to execute on behalf of the City.

end
4. FISCAL IMPACT
The expense for this contract is $1,794,529 and will be funded through:
500.5028.56015.12982 Corp Yard Renovation $ 230,340
553.5028.56015.12982 Corp Yard Renovation $1,500,000
954.5028.56020.19809 City Facility Improvements $ 64,189
Total $1,794,529
Upon approval of the appropriation, the estimated fund balance in the City Infrastructure Bond (553) fund at June 30, 2024 will be $271,146.
5. STRATEGIC PLAN GOALS
Goal 1: Provide for a safe community
b: Provide and maintain infrastructure necessary to ensure the safety of the public.
Goal 4: Provide outstanding public service
b: Provide facilities and services to meet customer expectations.
6. DISCUSSION AND BACKGROUND
The City of Orange Corporation Yard Renovation Project -Police Storage Facility (Phase 1A) includes a new police storage building with associated electrical improvements and lighting, storm drain improvements, and a new security perimeter wall fo...

Click here for full text